Posted on: Mon, 09/05/2022 - 21:43 By: admin
Northern Shouneh/ Southern Shouneh road.

Southern Shouneh Road:

 

al- Rama intersection / al- kafrain Widening and upgrading the existing 2- lane road to accommodate a 4-lane primary road with an approximate length of 17 kms.

 

Southern Shouneh Road:

 

Al- Ardah Intersection to southern shouneh Widening and upgrading the existing 2- lane road to accommodate a 4-lane primary road with an approximate length of 33 kms.

Northern shouneh / southern shoune road

 

waqqas area Widening and upgrading the existing 2- lane road to accommodate a 4-lane primary road with an approximate length of 11 kms. The works also included the design of a new bridge and widening of 2 existing bridges.

Services Performed Client Contract No. Cons. Cost Mill. US$ Year
Study, Design & Preparation of Specifications and Contract Documents MPWH 165/2006 91 2006-2011